27. apríl 2017


Estimate of Profitability
Saturday, December 28, 2002
Thorsteinn Sigurlaugsson has made a new Estimate of Profitability for The Karahnjukar Power Plant (november 2002) The project is still expected to result in big losses. This is not surprising as Alcoa's smelter will be much smaller than the one previously planned, about 26% less energy. The dam will however not cost much less than previously planned or only about 6%.

Here is the Estimate of Profitability (Word document)
Back

Your E-mail:
Add e-mail
remove e-mail
© Copyright 1998-2002, Iceland Nature Conservation Association
The Reykjavik Academy, Hringbraut 121, 107 Reykjavík - Phone: 551 2279 E-mail: nsi@mmedia.is